The Impact of Accidental Complexity on Estimates

At speakerconf Aruba, J.B. Rainsberger recently gave an enlightening talk which included discussion on the impact of accidental complexity to estimates.

In his talk, he pointed out that estimates are composed of accidental and essential complexity. It's often easy to estimate the essential complexity of a problem; however, estimating accidental complexity is an entirely different matter. This point really hit home for me. On my last project I often strongly disagreed with certain members of the team on estimates. I was often higher than the average, and much higher than the lowest estimates. J.B.'s talk really openend my eyes to a few points.
  • Not all developers consider both accidental and essential complexity while estimating
  • Features that touch accidentally complex portions of the system are harder to estimate as the accidental complexity can often be hard to completely understand. (If you completely understood it, you'd probably remove the accidental complexity)
  • Introducing technical debt increases accidental complexity, and as a side-effect invalidates previous estimates and increases the likelihood that future estimates will differ in size drastically.
The first two points had always been intuitive to me; however, it was good to hear the ideas clearly articulated from someone else's point of view. The last point was the one that really interested me.

I'm lucky enough to work for a company where I don't need to explain the benefits of addressing technical debt. As developers we sometimes consciously introduce technical debt when it will allow us a short-term benefit, and we address that technical debt when appropriate. I've always considered technical debt to be part of the developer's world, and I only mention it to the business when completing a feature takes longer than expected due to tech debt. I never considered the impact of technical debt on my ability to produce accurate estimates for the business.

J.B.'s talk made me ask myself a few questions about decisions I'd been making. Most importantly: If the business knew that I was taking a short-cut to deliver sooner, but it was going to damage estimates, would that be acceptable? I think that's an important question to consider if your client values estimates, and it's something I'll continue to ask myself in the future.

Tuesday, July 01, 2008

Agile: User Story Estimation Techniques

I recently published an article about estimation on InfoQ.

One of the great things about working as a consultant is the ability to try out many different ideas and adapting your personal favorite process to include things that work. This article gives the details about user story estimation techniques that I've found effective.....

read more...

Monday, July 23, 2007

Agile: Estimating

Following a previous entry, Stories are Placeholders not Buckets, Aman King states:
A blog entry from you on "estimating" and how you go about it (for various types of stories/buckets) would be a big help.
On the projects I'm generally involved in each story is estimated twice.

High level estimate
A high level estimate is usually helpful when a story is created. The high level estimate can be used to determine where it belongs in the current release (or in a subsequent release). I prefer that high level estimates be done by 3 or 4 developers. I also prefer the estimation scale be the same as the scale that will ultimately be used for the iteration estimate (i.e. don't use small, medium, large for the high level estimate and 1, 2, 3 for an iteration estimate). A high level estimate usually begins with a subject matter expert (often an analyst) explaining the details of the story. These details aren't the full details of the story, but the key aspects that effect the estimates. Following the explanation and any questions, the devs will independently determine their own estimate for the story. If all the devs agree (or are close) then you move on; however, if the estimates are wildly off then a conversation is had and the independent estimation process will occur again.

Iteration estimate
An iteration estimate is helpful for getting the entire team on the same page and determining which stories will be played in the next iteration. At ThoughtWorks we generally have an Iteration Planning Meeting (IPM) before each iteration. During the IPM the subject matter experts (again, usually analysts) explain all the details of the story. Following the explanation and any questions the entire* dev team will independently estimate the story. If the estimates are consistent, you move on, otherwise more discussion needs to occur and the independent estimates need to happen again (just like high level estimates).

Having 2 estimates is helpful for a few reasons. While the original estimate is good for planning purposes, the iteration estimate is better for determining what goes in the upcoming iteration. The iteration estimates should be more accurate because more people have the chance to participate in the estimation process, and (it's likely that) more information is known then when the high level estimate was taken. Given more accurate estimations and a known team velocity, predicting what can be done in each iteration should be a fairly easy task. Also, it's valuable to track if the high level estimates are generally lower or higher than the iteration estimates. Knowing this statistic can help make the high level estimates more accurate for release planning.

*Generally teams contain between 4-8 developers. For teams of this size having the entire team estimate seems to work well. However, if your team has more than 8 devs, I would suggest breaking into two estimation groups. Splitting the team clearly has consequences. At a minimum you will want each story to be started by at least one person who estimated it. Also, you'll need to find a way to communicate the details of each story to the half of the team not involved in estimation. I've seen this handled 2 ways.
  • The details of the story are presented to the entire team, then the team is broken to estimate.
  • Team Split 1 presents their stories to Team Split 2 following estimation and vice-versa.
I've used both, and they both seem to work fine.

Despite the consequences, splitting large teams for estimation has been much more effective in my experience.